Test Pile for Port Expansion in Cagban Jetty port is now starting for construction

Posted June 26, 2014
Written Jay-ar M. Arante

The Test Pile for the port Expansion of Cagban Jetty Port is now being started

According to Special Operation Officer III Jean Pontero of Caticlan Jetty Port, they are going to add 51 meters to the current port due to the limited dimension of the ramp that causes the slow operation of boats during low tide.

Pontero pointed that additional staircases will also be constructed and once finished, boats and ferries can dock simultaneously.

It was noted that the project was implemented by the Department of Transportation and Communication (DOTC) after they conducted an inspection on the island together with DILG Secretary Mar Roxas.

Pontero added that it they target to finish before the start of summer season next year.

For now they have more plans for the betterment of Caticlan and Cagban Jetty Port.